Run Time
Performance
Run Time
Time during which equipment is actively producing or a process is actively executing work.
Examples
- 01The run time of the CNC lathe is 18.5 hours a day, out of 22.5 hours planned for production.
- 02The weekly review compares run time with planned time by machine and shows where setups and waiting eat into it.
- 03Preparing tools outside the machine adds 1.5 hours of run time per day, confirmed over a month.