Procurement Lead Time
Procurement

Procurement Lead Time

Total time required to source, approve, order and receive purchased goods or services.

Examples

  1. 01Procurement lead time for a special pump is 10 weeks: 2 weeks for quotes, 1 week for internal approval and 7 weeks for delivery.
  2. 02When choosing between two suppliers, the buyer weighs procurement lead time together with quality and total cost, not price alone.
  3. 03Removing one approval level for orders below EUR 5,000 cuts procurement lead time by a week for most MRO purchases.