Safety Lead Time
Production Planning
Safety Lead Time
Planning buffer that offsets required receipt dates earlier than actual need to protect against time uncertainty.
Examples
- 01The planner sets a safety lead time of 2 days for a supplier that is often late, so material is planned to arrive early.
- 02Safety lead time is reviewed every quarter against the supplier's actual delivery performance, and removed once the supplier is on time for six months.
- 03When the supplier becomes reliable, the safety lead time is removed, reducing average stock by EUR 40,000.