CRP
Production Planning

CRP (Capacity Requirements Planning)

Capacity Requirements Planning

Calculation of detailed capacity load by work center based on planned and released orders.

Examples

  1. 01CRP shows that the grinding centre is loaded at 130 % in week 12 while turning is only at 60 %.
  2. 02When a large order is added, CRP is rerun to check which work centres become overloaded.
  3. 03Based on the CRP result, the planner moves 40 hours of grinding to Saturday and starts two orders a week earlier.