Critical Path
Project Management

Critical Path

Longest-duration dependency path through a project network that determines the earliest possible project completion.

Examples

  1. 01The critical path for the new warehouse runs through steel delivery, roof assembly and sprinkler approval: 34 weeks in total.
  2. 02At each steering meeting, the project manager reports first on tasks on the critical path, since any delay there moves the end date.
  3. 03When the sprinkler approval slips by two weeks on the critical path, the team overlaps racking installation to recover the time.